A project can have a compelling story and still be unready for a serious financing conversation. I see the difference often in infrastructure work. Someone identifies a need, names a location, circulates a concept drawing and requests a meeting. The energy is real. The project isn't ready yet.
Readiness isn't bureaucracy for its own sake. It's the work that turns an attractive idea into decisions others can test. It clarifies the problem, users, route, responsibilities, risks and evidence. Until those pieces connect, a financing conversation is being asked to solve a design problem.
An announcement is not a project
An announcement says what people hope will happen. A concept says what might be built. A ready project explains why the solution is needed, what it will deliver, what it will cost to operate, who has authority, which permissions it needs and what could change the plan.
The June 2023 PIDA PAP 2 prospectus shows that listed projects can be at different stages. It records Beira Port Development at pre-feasibility stage S2A. The Kenyan segment of the LAPSSET Railway is at feasibility stage S2B, the Ethiopian segment at pre-feasibility stage S2A and the South Sudanese segment at enabling environment and needs assessment stage S0. These labels tell us how much uncertainty remains and what work comes next.
Leaders should name the current stage, not borrow confidence from a later one. If demand hasn't been tested, say so. If the route isn't secured, say so. If no one has authority to operate, say so. Honest staging stops a project being presented as more mature than it is.
Preparation is a chain
Start with the problem, not the asset you want to build. What failure are we trying to remove? Who experiences it? What evidence shows how often it happens and what it costs? What alternatives did we consider? These questions stop a project becoming a solution in search of a user.
Next, define how the service will operate. Connect the technical design to a service standard, a demand profile, an implementation sequence and an organisation that can run it. Map land or route constraints, environmental and social effects, accessibility, procurement, permissions, existing systems and the work needed to maintain the asset.
A feasibility study isn't one document that makes uncertainty disappear. I see readiness as a chain of evidence, with each link answering a different question. Demand evidence tests use. Technical work tests delivery. Legal and institutional work tests authority. Social and environmental work tests acceptability. An operating plan tests durability. If one link is weak, keep the conversation at that level.
Accessibility belongs in this work from the start. If people with different abilities will use a service, access is a requirement, not a late fix. The same goes for digital interfaces, public information and movement through a physical asset. A project hasn't defined its service until it can say who can use it. Ask whether people who depend on the service can use it safely, clearly and independently.
Risk is a design choice
Every project has uncertainty. Readiness means naming it, deciding who can control it, recording a response and setting an escalation route. A construction delay, change in demand, border dependency, land constraint or maintenance failure shouldn't first appear in a crisis meeting.
The OECD's 2015 framework for infrastructure governance describes five phases in an asset's life cycle: evaluating needs, prioritising, preparing the project, constructing and operating it. It also links good governance to planning, project assessment, transparency, accountability and regulation. I take a clear lesson from that order: readiness doesn't end with a design. It must carry through construction and into operation.
The World Bank's 2020 reference guide makes a related point about roles. It distinguishes the proposer, appraiser, reviewer and decision maker. Those roles may sit in one organisation or several, but they shouldn't blur together. A project owner who can't name who reviews the evidence and who can approve the next step isn't ready for a high-stakes conversation.
The same discipline applies to risk. Put each risk beside the party best able to prevent, absorb or respond to it. Don't hide every uncertainty in a general promise to collaborate. Collaboration helps when it produces a decision, an owner and a recorded response.
A readiness conversation
When leaders ask me to help prepare a project, I'd rather start with a readiness conversation than a pitch. The first output should say what we know, what we're assuming, what's missing and what decision the next stage needs. It may conclude that the concept needs more work. That's progress. It keeps a polished presentation from carrying unresolved questions into the wrong room.
A useful readiness pack is brief enough to use and strong enough to challenge. It should cover the problem, evidence of demand, service definition, options considered, technical and site assumptions, permissions, environmental and social questions, accessibility, delivery route, operating responsibilities, key risks, decision rights, a work plan and a named sponsor. It should give sources and dates for material claims.
The financing conversation comes after this preparation. The project is then clear enough for a potential funding partner to examine, rather than a cloud of aspiration. More importantly, the project team can decide whether to proceed at all.
Questions for this week
Ask these questions this week. What problem can we prove? What does the user need? Which stage are we at on a defined readiness scale? Which evidence is still an assumption? Who can approve the next stage? Who will operate and maintain the result? Who owns each risk, and what will they do? What would make us stop, redesign or wait? Can the people this project serves use it safely and accessibly?
If answers are missing, don't hide the gap in a bigger meeting. Turn each gap into a task, name its owner and set a review date. Readiness doesn't kill ambition. It lets ambition move forward without asking others to guess what you mean.